ADP# 415

STRENGTHENING/CAPACITY BUILDING OF NEW NARCOTICS CONTROL WING OF EXCISE, TAXATION & NARCOTICS CONTROL DEPARTMENT IN TRIBAL DISTRICTS

Date of Approved PC-1   15.11.2019
Approved Cost   27.80  Million
Date of Completion:   June-2021
Revised Cost Estimate: 
Date of Completion
Forum of Approval:  DDWP
Total Duration  24 Months

 

PROJECT DESCRIPTION:

The project was approved by DDWP dated 15.11.2019 with a cost of Rs. 27.80 Million for a period of 24 months. Approved in the DDWP on 15-11-2019. Administrative Approval as per Concurrence of Finance Department NMA’s has been issued for Rs.27.80 (M) on Dated.10/12/2019.

  1. ETOs have been posted in these districts
  2. They have been tasked to establish offices there by approaching concerned Dy: Commissioners.
  3. Purchase  of furniture and other items is in process.
  4. An expenditure of Rs. 2.00 Million has been made during CFY 2020-21. Funds of Rs. 10.00 Million has been released during CFY (2021-22), but till date not utilized that funds.